In my MPCNC Primo (F) build I used 18mm electrical conduit for cable management, to prevent issues with dust and to ensure safe bend radii.
These parts are all designed to clamp around the ribbing of the conduit to lock it in place and provide smooth surfaces for cable entry and exit.
There are 3 parts:
I suggest installing Angled first to prevent clearance issues with the Direct attachment, especially on the X-Axis.
More information on the build can be found on the forums :
https://forum.v1engineering.com/t/new-build-in-bordeaux-france-2021-edition/28241